AMC Engineering Ltd – Aberdeen

  • Client – AMC Engineering Ltd
  • Project size – 532m²
  • Completion – 11 weeks
  • Office and Welfare Facilities
  • Ground floor – 3 No. Offices, 2 No. Meeting rooms, Reception/Waiting Area with Entrance Lobby, Server & Electrics room and WC’s
  • First floor – 13 No. Meeting rooms with linking corridor
  • Pitched roof with integrated downlights

AMC Engineering required an Office block and Welfare facility for their Aberdeen branch which Module-AR were awarded the contract to design, manufacture & install.

On the ground floor of the building there are 3 No. Offices of varying sizes, 2 No. Meeting rooms, a large Reception/Waiting Area with entrance Lobby, a Server & Electrics room, fully-fitted Kitchen, Cleaners’ Store, male & female WC’s and Corridor linking each room.

The first floor of the Module-AR Limited structure consists solely of 13 No. equal sized Meetings rooms, a Corridor linking each room and the internal Stairwell. The Offices, Reception, Meeting rooms and Corridors are all fitted with Primavera carpet tiles whereas the Kitchen and WC’s feature hard-wearing, easy to clean Polyflor Polysafe Vinyl flooring. Heat & Cool air conditioning was installed throughout the building along with window blinds and suspended ceilings.

Externally, the AMC Engineering building features Plastisol (plastic coated steel) cladding, plinths and fascia. A pitched roof with integrated downlights within the soffits and external door canopies were also installed to give the Module-AR Limited structure the look of a traditional build.

Only 2 days were required for Module-AR Limited to install the building with a total project completion time of 11 weeks – this is up to 50% faster than if the project was completed traditionally.